PJM-AI2-372
23.56 MW generation in Logan, IL · In queue since March 2023 · Proposed COD March 2020
23.56 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2020
Total Duration
3y 2m
Schedule
74 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-03-30
PJM-AI2-372 is a proposed wind generation project with a total capacity of 23.56 MW. The project is located in Logan County, Illinois, within the ComEd service area and the PJM Interconnection region. The project entered the PJM queue on March 3, 2023, with a proposed commercial operation date of March 30, 2020.
The interconnection agreement (IA) status for PJM-AI2-372 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Hill Topper 345kV line, involving a circuit increase.
Generated from interconnection queue and public data sources
State
IL
County
Logan
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Hill Topper 345kV (CIR Increase)
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-372