PJM-AI2-392
31.7 MW generation in Madison, OH · In queue since March 2023 · Proposed COD December 2025
31.7 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AI2-392 is a proposed solar generation project with a total capacity of 31.7 MW. The project is located in Madison County, Ohio, within the PJM Interconnection region. The queue entry date is March 2, 2023, with a proposed commercial operation date of December 31, 2025. The interconnection agreement status is currently "In Progress (unknown study)". The interconnecting utility is AEP.
The project consists of 31.7 MW of solar photovoltaic generation. It is listed in the PJM interconnection queue under queue ID PJM-AI2-392.
Generated from interconnection queue and public data sources
State
OH
County
Madison
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Beatty-London 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.