PJM-AI2-395
59.6 MW generation in White, IN · In queue since March 2023 · Proposed COD December 2025
59.6 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AI2-395 is a proposed solar generation project with a total capacity of 59.6 MW, located in White County, Indiana. The project is in the PJM interconnection queue, having entered on March 2, 2023, and is being developed within the AEP utility territory. The proposed commercial operation date is December 31, 2025.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Reynolds_x0013_Olive #1 345 kV location.
Generated from interconnection queue and public data sources
State
IN
County
White
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Reynolds_x0013_Olive #1 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-395