PJM-AI2-405
22.8 MW generation in Dekalb, IL · In queue since March 2023 · Proposed COD December 2026
22.8 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AI2-405 is a proposed solar generation project with a total capacity of 22.8 MW, located in Dekalb County, Illinois. The project is in the PJM interconnection queue, having entered on March 2, 2023, with a proposed commercial operation date of December 31, 2026. The interconnecting utility is ComEd.
The interconnection agreement for PJM-AI2-405 is currently listed as "In Progress (unknown study)". The point of interconnection is the Glidden-Waterman 138 kV line, requiring a circuit increase.
Generated from interconnection queue and public data sources
State
IL
County
Dekalb
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Glidden-Waterman 138 kV (CIR Increase)
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-405