PJM-AI2-420
20 MW hybrid in Dekalb, IL · In queue since March 2023 · Proposed COD December 2027
20 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PJM-AI2-420 is a proposed 20 MW hybrid solar and battery project located in Dekalb County, Illinois. The project, interconnected with ComEd, entered the PJM interconnection queue on March 2, 2023, with a proposed commercial operation date of December 31, 2027.
The interconnection agreement is currently listed as "In Progress (unknown study)". The point of interconnection is the Crego Road 138kV line, requiring a circuit increase.
Generated from interconnection queue and public data sources
State
IL
County
Dekalb
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Crego Road 138kV (CIR Increase)
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-420