PJM-AI2-429
22.2 MW generation in Lee, IL · In queue since March 2023 · Proposed COD December 2025
22.2 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AI2-429 is a proposed wind generation project with a total capacity of 22.2 MW, located in Lee County, Illinois. The project is interconnected to the ComEd utility and entered the PJM interconnection queue on March 9, 2023. Its proposed commercial operation date is December 31, 2025.
The interconnection agreement (IA) for PJM-AI2-429 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Mendota Hills 138 kV substation. The project is currently listed as active in the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
IL
County
Lee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Mendota Hills 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-429