PJM-AI2-431
2,138.85 MW generation in Atlantic, NJ · In queue since March 2023 · Proposed COD February 2030
2,138.85 MW
Capacity
1
Components
Offshore Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-02-28
PJM-AI2-431 is a proposed offshore wind generation project with a total capacity of 2138.85 MW. The project is located in Atlantic County, New Jersey, and is interconnected within the PJM Interconnection queue. The queue entry date is March 10, 2023, with a proposed commercial operation date of February 28, 2030. The project's interconnection agreement status is currently "In Progress (unknown study)".
The proposed project is being developed within the JCPL utility territory. The point of interconnection is the Larrabee Collector Station 230 kV. The project has appeared in recent news coverage regarding offshore wind development in the region.
Generated from interconnection queue and public data sources
State
NJ
County
Atlantic
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Larrabee Collector Station 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- POI Substation
- Station 2
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-431