PJM-AI2-433
7.28 MW generation in Clearfield, PA · In queue since March 2023 · Proposed COD February 2023
7.28 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
3y 2m
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-02-28
PJM-AI2-433 is a proposed solar generation project located in Clearfield County, Pennsylvania, with a total capacity of 7.28 MW. The project, which consists entirely of solar photovoltaic generation, is interconnected to the PENELEC utility network within the PJM Interconnection region.
The project entered the PJM interconnection queue on March 9, 2023, with a proposed commercial operation date of February 28, 2023. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
PA
County
Clearfield
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Dubois-Curwensville 34.5 kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-433