PJM-AI2-436
20 MW hybrid in Clearfield, PA · In queue since March 2023 · Proposed COD December 2026
20 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AI2-436 is a proposed 20 MW hybrid solar and battery project located in Clearfield County, Pennsylvania. The project, which consists of 20 MW of solar capacity, is in the PJM interconnection queue as of March 9, 2023, with a proposed commercial operation date of December 31, 2026. The point of interconnection is the Luthersburg - Curwensville 34.5 kV line.
The interconnection agreement status for the project is listed as "In Progress (unknown study)". The project is within the PENELEC utility territory.
Generated from interconnection queue and public data sources
State
PA
County
Clearfield
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Luthersburg - Curwensville 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-436