PJM-AI2-442
20 MW hybrid in Luzerne, PA · In queue since March 2023 · Proposed COD December 2027
20 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PJM-AI2-442 is a proposed 20 MW hybrid solar and battery project located in Luzerne County, Pennsylvania. The project, which consists of 20 MW of solar capacity, is in the PJM interconnection queue as of March 10, 2023, with a proposed commercial operation date of December 31, 2027. The interconnecting utility is PPL.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Salem-Beacon Power 69 kV line. The project is currently listed as active in the PJM queue.
Generated from interconnection queue and public data sources
State
PA
County
Luzerne
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Salem-Beacon Power 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-442