PJM-AI2-443
300 MW hybrid in Greene, PA · In queue since March 2023 · Proposed COD July 2027
300 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-10
PJM-AI2-443 is a proposed 300 MW hybrid solar and battery project located in Greene County, Pennsylvania. The project, which consists of 300 MW of solar generation, is in the PJM interconnection queue as of March 10, 2023, with a proposed commercial operation date of July 10, 2027. The interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project is interconnected to the North Longview 500 kV point of interconnection and is within the service area of utility APS. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
PA
County
Greene
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
North Longview 500 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NLONGVW 26 KV GEN 1
- POI Substation
- North Longview
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-443