Project PJM-AI2-443 — Project Summary

Queue ID
PJM-AI2-443
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Greene, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AI2-443

PJM-AI2-443BetaActiveSolarBatteryPJMLBNL + Live

300 MW hybrid in Greene, PA · In queue since March 2023 · Proposed COD July 2027

300 MW

Capacity

1

Components

Solar

3y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection

Total Duration

4y 4m

In Study38%
Queue EntryMar 10, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-10

About

PJM-AI2-443 is a proposed 300 MW hybrid solar and battery project located in Greene County, Pennsylvania. The project, which consists of 300 MW of solar generation, is in the PJM interconnection queue as of March 10, 2023, with a proposed commercial operation date of July 10, 2027. The interconnection agreement status is listed as "In Progress (unknown study)".

The proposed project is interconnected to the North Longview 500 kV point of interconnection and is within the service area of utility APS. The project is currently listed as active within the PJM queue.

Generated from interconnection queue and public data sources

Project Details

State

PA

County

Greene

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

APS

Entity

PJM

Service Type

Point of Interconnection

North Longview 500 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
NLONGVW 26 KV GEN 1
POI Substation
North Longview

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AI2-443