PJM-AI2-446
150 MW hybrid in Cambria, PA · In queue since March 2023 · Proposed COD December 2027
150 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PJM-AI2-446 is a proposed 150 MW hybrid solar and battery project located in Cambria County, Pennsylvania. The project consists of 150 MW of solar generation. It is listed in the PJM interconnection queue as of March 10, 2023, with a proposed commercial operation date of December 31, 2027. The point of interconnection is the Medera - Westover South 115 kV substation.
The interconnection agreement for PJM-AI2-446 is currently listed as "In Progress (unknown study)". The project is within the PENELEC utility service area. Recent news coverage of the project may exist.
Generated from interconnection queue and public data sources
State
PA
County
Cambria
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Medera - Westover South 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SOUTH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.