PJM-AI2-447
87.3 MW generation in Highland, OH · In queue since March 2023 · Proposed COD September 2023
87.3 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
6 months
Schedule
32 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-09-30
PJM-AI2-447 is a proposed solar generation project with a total capacity of 87.3 MW. The project is located in Highland County, Ohio, and is interconnected within the PJM Interconnection queue. The queue entry date is March 10, 2023, with a proposed commercial operation date of September 30, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project is to be interconnected with AEP at the Hillsboro-Wildcat 138kV point of interconnection.
Generated from interconnection queue and public data sources
State
OH
County
Highland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Hillsboro-Wildcat 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-447