PJM-AI2-452
51.8 MW generation in Hardin, OH · In queue since March 2023 · Proposed COD December 2025
51.8 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
The proposed project PJM-AI2-452 is a 51.8 MW solar generation project located in Hardin County, Ohio. The project is interconnected within the PJM Interconnection queue, with queue entry date of March 11, 2023, and a proposed commercial operation date of December 31, 2025. The interconnection agreement is currently listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection is the Gunn Road 345 kV line.
The development project consists solely of solar generation, with a total capacity of 51.8 MW. The project is currently listed as "active" within the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Hardin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Gunn Road 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-452