PJM-AI2-456
150 MW storage in King George, VA · In queue since March 2023 · Proposed COD September 2027
150 MW
Capacity
1
Components
Battery
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-15
PJM-AI2-456 is a proposed 150 MW battery storage project located in King George County, Virginia. The project, which consists entirely of battery storage, is being developed within the Dominion service area.
The project is listed in the PJM interconnection queue with an entry date of March 11, 2023. Its proposed commercial operation date is September 15, 2027. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
King George
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Birchwood - Fines Corner 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-456