PJM-AI2-461
173 MW generation in Kankakee, IL · In queue since March 2023 · Proposed COD May 2026
173 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 2m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-01
The proposed PJM-AI2-461 project is a 173 MW wind generation project located in Kankakee County, Illinois. The project is being developed within the ComEd service area and has an interconnection queue entry date of March 10, 2023, in the PJM Interconnection queue. The proposed commercial operation date is May 1, 2026.
The interconnection agreement status for the project is listed as "In Progress (unknown study)". The point of interconnection is the Wilton Center - Loretto 345 kV line, with a circuit increase.
Generated from interconnection queue and public data sources
State
IL
County
Kankakee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Wilton Center - Loretto 345 kV(CIR Increase)
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-461