PJM-AI2-462
48 MW generation in Kankakee, IL · In queue since March 2023 · Proposed COD May 2027
48 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-01
PJM-AI2-462 is a proposed solar generation project with a total capacity of 48 MW, located in Kankakee County, Illinois. The project is in the PJM interconnection queue as of March 10, 2023, with a proposed commercial operation date of May 1, 2027. The interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project is located within the ComEd service area. The point of interconnection is AD1-100 345kV (CIR Increase).
Generated from interconnection queue and public data sources
State
IL
County
Kankakee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
AD1-100 345kV (CIR Increase)
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM