PJM-AI2-464
5.8 MW generation in Union, PA · In queue since March 2023 · Proposed COD May 2027
5.8 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-01
PJM-AI2-464 is a proposed solar generation project with a total capacity of 5.8 MW, located in Union County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 10, 2023. The proposed commercial operation date is May 1, 2027. The interconnecting utility is PPL, and the point of interconnection is the Laurelton-Mifflinburg 69 kV line.
The interconnection agreement status is currently "In Progress (unknown study)". The developer is not specified in the available data.
Generated from interconnection queue and public data sources
State
PA
County
Union
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Laurelton-Mifflinburg 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-464