PJM-AI2-466
5.8 MW generation in Union, PA · In queue since March 2023 · Proposed COD May 2027
5.8 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-01
PJM-AI2-466 is a proposed solar generation project with a total capacity of 5.8 MW. The project is located in Union County, Pennsylvania, within the PJM Interconnection region, and is being managed by the utility PPL. The project entered the PJM queue on March 11, 2023, with a proposed commercial operation date of May 1, 2027.
The interconnection agreement for PJM-AI2-466 is currently listed as "In Progress (unknown study)". The point of interconnection is the Laurelton - Mifflinburg 69 kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
PA
County
Union
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Laurelton - Mifflinburg 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM