PJM-AI2-480
5.8 MW generation in Crawford, PA · In queue since March 2023 · Proposed COD May 2027
5.8 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-01
PJM-AI2-480 is a proposed solar generation project with a total capacity of 5.8 MW, located in Crawford County, Pennsylvania. The project is in the PJM interconnection queue, having entered on March 11, 2023, with a proposed commercial operation date of May 1, 2027. The interconnecting utility is PENELEC, and the point of interconnection is the Crawford 34.5 kV substation. The interconnection agreement status is currently "In Progress (unknown study)".
The development project consists solely of solar generation, with a capacity of 5.8 MW.
Generated from interconnection queue and public data sources
State
PA
County
Crawford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Crawford 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-480