PJM-AI2-486
14 MW generation in Fayette, PA · In queue since March 2023 · Proposed COD December 2028
14 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
PJM-AI2-486 is a proposed solar generation project located in Fayette County, Pennsylvania, within the PJM Interconnection region. The development project, with a total capacity of 14 MW, is being managed within the APS utility territory. It entered the PJM interconnection queue on March 10, 2023, and has a proposed commercial operation date of December 1, 2028.
The project's interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Bethelboro - Connellsville 25 kV line.
Generated from interconnection queue and public data sources
State
PA
County
Fayette
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Bethelboro - Connellsville 25 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.