PJM-AI2-493
18.2 MW generation in Somerset, PA · In queue since March 2023 · Proposed COD August 2023
18.2 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
5 months
Schedule
33 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-08-31
PJM-AI2-493 is a proposed wind generation project located in Somerset County, Pennsylvania, within the PJM Interconnection region. The project, with a total capacity of 18.2 MW, consists entirely of wind turbines. The queue entry date for PJM-AI2-493 is March 11, 2023, with a proposed commercial operation date of August 31, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project is located within the PENELEC utility service area and its point of interconnection is the New Baltimore 115kV (Stony Creek) substation. The developer is not specified in the queue data. The project is currently listed as active within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
PA
County
Somerset
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
New Baltimore 115kV (Stony Creek)
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-493