PJM-AJ1-012
354.4 MW storage in Lake, IL · In queue since May 2023 · Proposed COD June 2027
354.4 MW
Capacity
1
Components
Battery
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
PJM-AJ1-012 is a proposed battery storage project with a total capacity of 354.4 MW. The project is located in Lake County, Illinois, within the ComEd service area and the PJM Interconnection region. The queue entry date is May 24, 2023, with a proposed commercial operation date of June 1, 2027.
The interconnection agreement (IA) for PJM-AJ1-012 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is at the Waukegan Unit 8 CIR Transfer location.
Generated from interconnection queue and public data sources
State
IL
County
Lake
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Waukegan Unit 8 CIR Transfer
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AJ1-012