PJM-AJ1-013
250 MW storage in Will, IL · In queue since May 2023 · Proposed COD June 2027
250 MW
Capacity
1
Components
Battery
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
PJM-AJ1-013 is a proposed 250 MW battery storage project located in Will County, Illinois. The project is interconnected within the PJM Interconnection queue, with an initial queue entry date of May 24, 2023. The proposed commercial operation date is June 1, 2027.
The interconnection agreement (IA) for the project is currently listed as "In Progress (unknown study)". The designated point of interconnection (POI) is the Will County Unit 4 CIR Transfer. The project is within the ComEd utility territory.
Generated from interconnection queue and public data sources
State
IL
County
Will
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Will County Unit 4 CIR Transfer
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AJ1-013