PJM-AJ1-016
100 MW storage in Cambria, PA · In queue since June 2023 · Proposed COD November 2028
100 MW
Capacity
1
Components
Battery
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-09
PJM-AJ1-016 is a proposed 100 MW battery storage project located in Cambria County, Pennsylvania. The project, which consists entirely of battery storage, is interconnected within the PJM Interconnection queue as of June 7, 2023. The proposed commercial operation date is November 9, 2028.
The interconnection agreement for the project with PENELEC is currently in progress, with the specific study type unknown. The point of interconnection is the Cambria Slope 115 kV substation.
Generated from interconnection queue and public data sources
State
PA
County
Cambria
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Cambria Slope 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- EBENSBUR13 KV NUG GE
- POI Substation
- Cambria Slope Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.