PJM-AJ1-020
86.38 MW generation in Caroline, VA · In queue since June 2023 · Proposed COD December 2029
86.38 MW
Capacity
1
Components
Solar
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-15
PJM-AJ1-020 is a proposed solar generation project with a total capacity of 86.38 MW. The project is located in Caroline County, Virginia, within the Dominion service area. It is listed in the PJM interconnection queue as of June 30, 2023, with a proposed commercial operation date of December 15, 2029. The interconnection agreement (IA) status is currently "In Progress (unknown study)".
The project consists of 86.38 MW of solar photovoltaic generation. The point of interconnection (POI) is the St. Johns _x0013_ Woodpecker 115 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Caroline
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
St. Johns _x0013_ Woodpecker 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AJ1-020