16.2 MW generation in Caroline, VA · In queue since June 2023 · Proposed COD December 2029
16.2 MW
Capacity
1
Components
Solar
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-15
PJM-AJ1-021 is a proposed solar generation project with a total capacity of 16.2 MW. The project is located in Caroline County, Virginia, within the Dominion service area. It entered the PJM interconnection queue on June 30, 2023, with a proposed commercial operation date of December 15, 2029.
The interconnection agreement for PJM-AJ1-021 is currently listed as "In Progress (unknown study)". The point of interconnection is the Woodpecker _x0013_ Slabtown 115 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Caroline
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Woodpecker _x0013_ Slabtown 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.