PJM-AJ1-023
70 MW generation in Trumbull, OH · In queue since June 2023 · Proposed COD December 2024
70 MW
Capacity
1
Components
Gas
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 6m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
PJM-AJ1-023 is a proposed 70 MW gas-fired generation project located in Trumbull County, Ohio. The project is interconnected within the PJM Interconnection queue, having entered the queue on June 30, 2023. The proposed commercial operation date is December 1, 2024.
The interconnection agreement for the project with utility ATSI is currently listed as "In Progress (unknown study)". The point of interconnection is the Trumbull 345 kV substation. The project is listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Trumbull
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Trumbull 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AJ1-023