PNM-IA-PNM-2014-02
80 MW generation in San Juan, NM · In queue since February 2014 · Proposed COD March 2018
80 MW
Capacity
1
Components
Gas
12y 3m
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
4y 1m
Schedule
100 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2018-03-01
The proposed project PNM-IA-PNM-2014-02 is an 80 MW gas-fired generation project located in San Juan County, New Mexico. The project is being developed by PNM (Public Service Company of New Mexico). It consists of a single 80 MW gas component.
The project is in the Public Service Company of New Mexico interconnection queue with an entry date of February 13, 2014. Its proposed commercial operation date is March 1, 2018, and the Interconnection Agreement (IA) has been executed. The point of interconnection is PNM-GPD San Juan Unit 5.
Generated from interconnection queue and public data sources
State
NM
County
San Juan
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
PNM-GPD San Juan Unit 5
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2014-02