PNM-IA-PNM-2015-01
29 MW generation in Doa Ana Cty, NM · In queue since July 2015 · Proposed COD November 2021
29 MW
Capacity
1
Components
Geothermal
10y 10m
In Queue
IA Executed
IA Status
COD target: 2021
Total Duration
6y 4m
Schedule
55 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2021-11-01
The proposed PNM-IA-PNM-2015-01 project is a 29 MW geothermal generation project located in Doa Ana County, New Mexico. The project is interconnected to the Public Service Company of New Mexico (PNM) via the Picacho Station. It is listed in the PNM interconnection queue with an entry date of July 28, 2015.
The project's proposed commercial operation date is November 1, 2021, and the interconnection agreement has been executed. The developer is listed as PNM.
Generated from interconnection queue and public data sources
State
NM
County
Doa Ana Cty
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Picacho Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2015-01