NMRD Data Center IV
140 MW generation in Sandoval, NM · In queue since January 2017 · Proposed COD November 2022
140 MW
Capacity
1
Components
Solar
9y 4m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
5y 10m
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2022-11-01
The NMRD Data Center IV project is a proposed 140 MW solar generation project located in Sandoval County, New Mexico. Interconnecting to the Public Service Company of New Mexico (PNM) grid at the Rio Puerco Station, the project entered the PNM interconnection queue as queue ID PNM-IA-PNM-2017-10 on January 31, 2017. The proposed commercial operation date was November 1, 2022, and the Interconnection Agreement (IA) has been executed.
The development project has been featured in recent news coverage.
Generated from interconnection queue and public data sources
State
NM
County
Sandoval
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Rio Puerco Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14