PNM-IA-PNM-2017-11
74.9 MW hybrid in Torrance, NM · In queue since June 2017 · Proposed COD June 2020
74.9 MW
Capacity
2
Components
Solar + Battery
8y 11m
In Queue
System Impact Study
IA Status
COD target: 2020
Total Duration
3 years
Schedule
72 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-06-01
The proposed project, identified as PNM-IA-PNM-2017-11, is a 74.9 MW hybrid solar and battery energy storage development in Torrance County, New Mexico. The project consists of a 49.9 MW solar array coupled with a 25 MW battery energy storage system. It is being developed within the Public Service Company of New Mexico (PNM) interconnection queue, under the queue ID PNM-IA-PNM-2017-11.
The project entered the queue on June 5, 2017, with a proposed commercial operation date of June 1, 2020. Its interconnection status is currently listed as "System Impact Study". The point of interconnection is the Britton 115 kV Substation.
Generated from interconnection queue and public data sources
State
NM
County
Torrance
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Britton 115 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2017-11