PNM-IA-PNM-2018-03
100 MW generation in San Juan, NM · In queue since July 2018 · Proposed COD June 2021
100 MW
Capacity
1
Components
Solar
7y 10m
In Queue
Suspended
IA Status
COD target: 2021
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-06-01
The proposed project, identified as PNM-IA-PNM-2018-03, is a 100 MW solar generation facility located in San Juan County, New Mexico. The developer is DESRI Rockmont Development. The project is interconnected to the Public Service Company of New Mexico (PNM) via the San Juan 345 kV Bus.
The project is in the PNM interconnection queue with an entry date of July 27, 2018. The proposed commercial operation date was June 1, 2021. The interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
NM
County
San Juan
Grid Region
Mountain West
Market
—
Developer
DESRI Rockmont Development
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
San Juan 345 kV Bus
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2018-03