PNM-IA-PNM-2019-05
96 MW hybrid in Santa Fe, NM · In queue since April 2019 · Proposed COD December 2021
96 MW
Capacity
1
Components
Solar
7y 1m
In Queue
IA Executed
IA Status
COD target: 2021
Total Duration
2y 8m
Schedule
54 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2021-12-01
The proposed project PNM-IA-PNM-2019-05 is a 96 MW solar and battery hybrid development located in Santa Fe County, New Mexico. The project, under development by PNM, consists of 96 MW of solar generation capacity. It is interconnected to the Public Service Company of New Mexico (PNM) grid.
The project is listed in the PNM interconnection queue with an entry date of April 23, 2019. The proposed commercial operation date is December 1, 2021, and the interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
NM
County
Santa Fe
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Randho Viejo Zia/Rodeo _x0013_ El Dorado Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2019-05