PNM-IA-PNM-2019-08
125 MW hybrid in Mckinley, NM · In queue since April 2019 · Proposed COD December 2022
125 MW
Capacity
1
Components
Solar
7y 1m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
3y 8m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2022-12-01
The proposed project PNM-IA-PNM-2019-08 is a 125 MW solar and battery hybrid project located in McKinley County, New Mexico. The developer is RWE Solar Dev. The project consists of 125 MW of solar capacity.
The project is in the Public Service Company of New Mexico (PNM) interconnection queue, with an entry date of April 22, 2019. The proposed commercial operation date is December 1, 2022, and the interconnection agreement has been executed. The point of interconnection is the Yah-Ta-Hey _x0013_ Pitt Midway Line.
Generated from interconnection queue and public data sources
State
NM
County
Mckinley
Grid Region
Mountain West
Market
—
Developer
RWE Solar Dev
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Yah-Ta-Hey _x0013_ Pitt Midway Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2019-08