PNM-IA-PNM-2019-12
80 MW generation in Torrance, NM · In queue since April 2019 · Proposed COD September 2020
80 MW
Capacity
1
Components
Wind
7y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2020
Total Duration
1y 5m
Schedule
69 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-09-01
The proposed project, identified as PNM-IA-PNM-2019-12, is an 80 MW wind generation facility in Torrance County, New Mexico. The project is being developed within the Public Service Company of New Mexico (PNM) service area. It is interconnected to the Clines Corners 345 kV Switching Station.
The project entered the PNM interconnection queue on April 23, 2019, with a proposed commercial operation date of September 1, 2020. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
NM
County
Torrance
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Clines Corners 345 kV Switching Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2019-12