PNM-IA-PNM-2019-18
100 MW storage in Bernalillo, NM · In queue since April 2019 · Proposed COD March 2022
100 MW
Capacity
1
Components
Battery
7y 1m
In Queue
Suspended
IA Status
COD target: 2022
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-03-01
PNM-IA-PNM-2019-18 is a proposed 100 MW battery storage project located in Bernalillo County, New Mexico. The project, developed by PNM, entered the Public Service Company of New Mexico interconnection queue on April 22, 2019, with a proposed commercial operation date of March 1, 2022. The point of interconnection is the Oso Negro West Mesa 115 kV Line.
The project's interconnection status is currently listed as "suspended," and the Interconnection Agreement (IA) status is also "Suspended."
Generated from interconnection queue and public data sources
State
NM
County
Bernalillo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Oso Negro West Mesa 115 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2019-18