PNM-IA-PNM-2020-01
145 MW generation in Guadalupe, NM · In queue since January 2020 · Proposed COD December 2021
145 MW
Capacity
1
Components
Wind
6y 4m
In Queue
IA Executed
IA Status
COD target: 2021
Total Duration
1y 11m
Schedule
54 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2021-12-01
The proposed PNM-IA-PNM-2020-01 project is a 145 MW wind generation facility located in Guadalupe County, New Mexico. The project is being developed within the Public Service Company of New Mexico (PNM) service area.
The project is listed in the PNM interconnection queue with an entry date of January 16, 2020, and a proposed commercial operation date of December 1, 2021. The interconnection agreement (IA) for the project has been executed. The point of interconnection is the Aragonne Wind Guadalupe 345 kV Station.
Generated from interconnection queue and public data sources
State
NM
County
Guadalupe
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Aragonne Wind Guadalupe 345 kV Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2020-01