PNM-IA-PNM-2020-04
400 MW hybrid in Bernalillo, NM · In queue since January 2020 · Proposed COD September 2023
400 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
3y 8m
Schedule
33 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2023-09-01
PNM-IA-PNM-2020-04 is a proposed 400 MW hybrid solar and battery project located in Bernalillo County, New Mexico. The development project, which consists of 400 MW of solar power, is in the Public Service Company of New Mexico (PNM) interconnection queue, with an entry date of January 17, 2020. The proposed commercial operation date is September 1, 2023, and the Interconnection Agreement (IA) has been executed.
The point of interconnection (POI) for the project is the Bernalillo Solar West Mesa - Sandia 345 kV Line. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NM
County
Bernalillo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Bernalillo Solar West Mesa - Sandia 345 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.