PNM-IA-PNM-2020-05
80 MW generation in San Juan, NM · In queue since January 2020 · Proposed COD May 2022
80 MW
Capacity
1
Components
Gas
6y 4m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
2y 4m
Schedule
49 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2022-05-01
The proposed project PNM-IA-PNM-2020-05 is an 80 MW gas-fired generation facility in San Juan County, New Mexico. The project is being developed by PNM _x0013_ Generation and is interconnected with the Public Service Company of New Mexico (PNM) at the San Juan Switching Station.
The project is in the PNM interconnection queue, with an initial queue entry date of January 17, 2020. The proposed commercial operation date is May 1, 2022, and the Interconnection Agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
NM
County
San Juan
Grid Region
Mountain West
Market
—
Developer
PNM _x0013_ Generation
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
San Juan Switching Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2020-05