PNM-IA-PNM-2020-06
90 MW hybrid in Mckinley, NM · In queue since May 2020 · Proposed COD June 2023
90 MW
Capacity
1
Components
Solar
6 years
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 1m
Schedule
36 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-01
PNM-IA-PNM-2020-06 is a proposed 90 MW hybrid solar and battery project located in McKinley County, New Mexico. The project, which consists of 90 MW of solar generation, is in the Public Service Company of New Mexico (PNM) interconnection queue, under the queue ID PNM-IA-PNM-2020-06. The queue entry date is May 18, 2020, and the proposed commercial operation date is June 1, 2023. The project's interconnection status is currently in the System Impact Study phase.
The point of interconnection for the proposed project is the Yah-Ta-Hey Substation. The developer is PNM. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
NM
County
Mckinley
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Yah-Ta-Hey Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2020-06