PNM-IA-PNM-2020-07
100 MW hybrid in San Juan, NM · In queue since May 2020 · Proposed COD December 2023
100 MW
Capacity
1
Components
Solar
6 years
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 7m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
The proposed project PNM-IA-PNM-2020-07 is a 100 MW hybrid Solar+Battery development project located in San Juan County, New Mexico. The project consists of 100 MW of solar capacity. It is interconnected to the Public Service Company of New Mexico (PNM) via the Bisti 230 kV Substation.
The project is currently in the Public Service Company of New Mexico interconnection queue, with an entry date of May 15, 2020. Its proposed commercial operation date is December 1, 2023. The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
NM
County
San Juan
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Bisti 230 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2020-07