PNM-IA-PNM-2020-11
90 MW hybrid in Mckinley, NM · In queue since October 2020 · Proposed COD May 2023
90 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Suspended
IA Status
COD target: 2023
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-05-01
The proposed project PNM-IA-PNM-2020-11 is a 90 MW hybrid solar and battery energy storage development in McKinley County, New Mexico. The project, under development by Ambrosia Solar, consists of 90 MW of solar capacity. It is located close to the Ambrosia Lake 115 kV Substation.
The project is in the Public Service Company of New Mexico (PNM) interconnection queue, with an original queue entry date of October 14, 2020, and a proposed commercial operation date of May 1, 2023. Its interconnection agreement (IA) status is currently listed as suspended. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NM
County
Mckinley
Grid Region
Mountain West
Market
—
Developer
Ambrosia Solar
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Close to Ambrosia Lake 115 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2020-11