Wildcat Solar Power Plant
90 MW hybrid in Mckinley, NM · In queue since October 2020 · Proposed COD May 2023
90 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Suspended
IA Status
COD target: 2023
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-05-01
The Wildcat Solar Power Plant is a proposed 90 MW hybrid solar and battery energy storage project located in McKinley County, New Mexico. The development project consists of 90 MW of solar photovoltaic generation. It is listed in the Public Service Company of New Mexico (PNM) interconnection queue as project number PNM-IA-PNM-2020-12, with an interconnection queue entry date of October 14, 2020, and a proposed commercial operation date of May 1, 2023. The project's interconnection agreement status is currently listed as Suspended.
The Wildcat Solar Power Plant has been featured in recent news coverage related to industry and development.
Generated from interconnection queue and public data sources
State
NM
County
Mckinley
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
YN line 115 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.