PNM-IA-PNM-2020-21
100 MW hybrid in Valencia, NM · In queue since October 2020 · Proposed COD November 2023
100 MW
Capacity
1
Components
Solar
5y 7m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
3y 1m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2023-11-01
PNM-IA-PNM-2020-21 is a proposed 100 MW hybrid solar and battery energy storage project located in Valencia County, New Mexico. The development project, under the developer NextEra Energy, is interconnected to the Public Service Company of New Mexico (PNM) via the Sky Station point of interconnection. The project entered the PNM interconnection queue on October 14, 2020, with a proposed commercial operation date of November 1, 2023. The interconnection agreement has been executed.
The project consists of 100 MW of solar generation capacity. The project has appeared in recent news coverage, with seven articles categorized as deals and regulatory matters.
Generated from interconnection queue and public data sources
State
NM
County
Valencia
Grid Region
Mountain West
Market
—
Developer
NextEra Energy
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Sky Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26