Zinnia Energy
50 MW storage in Bernalillo, NM · In queue since June 2021 · Proposed COD June 2024
50 MW
Capacity
1
Components
Battery
4y 11m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
3 years
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2024-06-01
The Zinnia Energy project is a proposed 50 MW battery storage project located in Bernalillo County, New Mexico. The project is in the Public Service Company of New Mexico (PNM) interconnection queue, identified as PNM-IA-PNM-2021-01, with an initial queue entry date of June 1, 2021. The proposed commercial operation date is June 1, 2024, and the interconnection agreement has been executed.
The project consists of 50 MW of battery storage capacity. The point of interconnection is the Reeves 115kV Line. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NM
County
Bernalillo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Reeves 115kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Zinnia Energy