Globemallow Solar
150 MW hybrid in Santa Fe, NM · In queue since July 2021 · Proposed COD December 2024
150 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
3y 5m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2024-12-01
Globemallow Solar is a proposed 150 MW hybrid solar and battery energy storage project located in Santa Fe County, New Mexico. The development project consists of 150 MW of solar photovoltaic generation. It is listed in the Public Service Company of New Mexico (PNM) interconnection queue as project number PNM-IA-PNM-2021-07, with an interconnection queue entry date of July 9, 2021. The project's proposed commercial operation date is December 1, 2024, and the interconnection agreement has been executed.
The project is located in the Western region and is interconnected to the Diamond Tail-Clines Corners point of interconnection. The interconnection agreement status is listed as "IA Executed." The project has appeared in recent news coverage regarding renewable energy development in New Mexico.
Generated from interconnection queue and public data sources
State
NM
County
Santa Fe
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Diamond Tail-Clines Corners
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Globemallow Solar