PNM-IA-PNM-2021-08
200 MW generation in Guadalupe, NM · In queue since June 2021 · Proposed COD November 2024
200 MW
Capacity
1
Components
Solar
4y 11m
In Queue
IA Pending
IA Status
COD target: 2024
Total Duration
3y 5m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-01
The proposed project PNM-IA-PNM-2021-08 is a 200 MW solar generation project located in Guadalupe County, New Mexico. The developer is PNM (Public Service Company of New Mexico). It consists of 200 MW of solar photovoltaic generation.
The project is in the Public Service Company of New Mexico interconnection queue, with an entry date of June 11, 2021. The proposed commercial operation date is November 1, 2024, and the Interconnection Agreement (IA) status is currently listed as "IA Pending." The point of interconnection is the Taiban-345 kV Line.
Generated from interconnection queue and public data sources
State
NM
County
Guadalupe
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Taiban- 345 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.