PNM-IA-PNM-2021-10
300 MW hybrid in Bernalillo, NM · In queue since July 2021 · Proposed COD June 2025
300 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
3y 11m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-06-01
PNM-IA-PNM-2021-10 is a proposed 300 MW hybrid solar and battery project located in Bernalillo County, New Mexico. The development project, which appeared in the Public Service Company of New Mexico (PNM) interconnection queue on July 9, 2021, consists of 300 MW of solar capacity. NextEra Energy is listed as the developer.
The project is in the PNM queue and has an interconnection agreement (IA) executed. The proposed commercial operation date is June 1, 2025, and the point of interconnection is the Pajarito-345 kV Substation.
Generated from interconnection queue and public data sources
State
NM
County
Bernalillo
Grid Region
Mountain West
Market
—
Developer
NextEra Energy
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Pajarito- 345 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.