PNM-IA-PNM-2021-19
150 MW generation in Valencia, NM · In queue since July 2021 · Proposed COD July 2025
150 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Pending
IA Status
COD target: 2025
Total Duration
4 years
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-07-01
The proposed project PNM-IA-PNM-2021-19 is a 150 MW solar generation project located in Valencia County, New Mexico. The project is in the Public Service Company of New Mexico (PNM) interconnection queue, with an entry date of July 12, 2021. The proposed commercial operation date is July 1, 2025. The point of interconnection is the Huning Ranch Station.
The project's interconnection agreement (IA) status is currently listed as "IA Pending." The developer is PNM. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
NM
County
Valencia
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Huning Ranch Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PNM-IA-PNM-2021-19